The Minister of Works, David Umahi, has reversed his earlier position on the relationship between the Lagos-Calabar Coastal Highway and the East-West Road reconstruction, insisting that the two projects will proceed independently, amid growing questions over the alignment and future of President Bola Tinubu’s flagship coastal highway.
Umahi said the President had directed that the 750-kilometre highway, which traverses nine coastal states, must be completed as originally planned, dismissing suggestions that the reconstruction of the East-West Road would replace or undermine the coastal project.
He also disclosed that Tinubu was expected to officially commission Section One of the coastal highway later this month or in early December.
The minister spoke on Sunday, November 22, 2026, during an inspection of bridges on Sections One and Two of the highway. His position comes after weeks of uncertainty over the government’s plans for the coastal route, following his earlier comments that the highway would be diverted through the existing East-West Road.
In a statement issued on Monday by his Senior Special Assistant on Media, Francis Nwaze, Umahi said the coastal highway remained a priority of the Tinubu administration, adding that the resident had given a clear directive on its completion.
The statement read, “The Honourable Minister of Works, Senator Engr. David Umahi, CON, has reaffirmed President Bola Ahmed Tinubu’s commitment to completing the 750-kilometre Lagos-Calabar Coastal Highway, describing the project as a profitable national investment capable of generating revenue, attracting private investors and unlocking tourism and industrial opportunities.
“Nothing will happen to the 750-kilometre Lagos-Calabar Coastal Highway, which passes through the nine coastal states. The President has directed that the project must be completed as envisaged.
“The official commissioning of Section 1 by President Tinubu is expected this month or early December. Also, the reconstruction of the East-West Road is an additional commitment by President Tinubu and does not replace or affect the Lagos-Calabar Coastal Highway, stressing that the President is pursuing multiple major infrastructure projects simultaneously across the country.”
The minister’s latest clarification follows controversy triggered by his October 12 remarks that Tinubu had directed the government to use the existing East-West Road rather than construct a new alignment along parts of the coastal corridor.
Umahi had quoted the President as saying, “Divert, do not do any new alignments. Pass the coastal highway through the existing East-West Road.”
However, following the backlash and questions over whether the original coastal route had been abandoned, the minister subsequently clarified that the highway’s alignment remained intact and that the East-West Road reconstruction was an additional connection rather than a replacement.
The latest statement further reinforces that position, although the shifting explanations have raised questions about the government’s communication on the scope and alignment of the multibillion-naira infrastructure project.
In another interview on Arise Television on October 23, Umahi said the entire 750km highway would be completed within the next three years and maintained that the project was being designed, procured, and constructed in sections.
“I believe that within the next three years plus, the President will complete the project,” he said.
He also acknowledged that there was no single comprehensive engineering design covering the entire 750km route, explaining that environmental assessments, soil investigations and detailed engineering designs were being undertaken section by section.
The coastal highway, whose construction commenced in March 2024, is designed to connect Lagos, Ogun, Ondo, Edo, Delta, Bayelsa, Rivers, Akwa Ibom and Cross River states.
Umahi, however, sought to make a fresh case for the project’s economic viability, describing it as a national investment capable of generating revenue, attracting private capital and opening up opportunities in tourism and industrial development.
According to him, the use of concrete pavement and solar-powered infrastructure would enable the Federal Government to benefit from carbon credits, while the highway would accommodate commercial and tourism facilities.
He added that the project would provide opportunities for investors to recover their investments through different commercial arrangements.
The minister said the highway would also feature tourism facilities, factories, CCTV surveillance and other infrastructure capable of supporting economic activities along the coastal corridor.
He described the project as one of the administration’s major infrastructure commitments, alongside the ongoing 1,068-kilometre Sokoto-Badagry Road.
Umahi also defended the administration’s infrastructure programme, commending Tinubu for pursuing several major road projects simultaneously across the country.
He urged Nigerians, particularly residents of the South-East living in Lagos, to support the President, arguing that the administration had delivered significant infrastructure projects to the region.
The minister further cited declining inflation, improved access to foreign exchange for businesses and the absence of industrial action by the Academic Staff Union of Universities as developments Nigerians should appreciate.
Meanwhile, the Federal Government has ordered a three-week nationwide emergency rehabilitation of major federal highways ahead of the Christmas and New Year festivities and the January 2027 elections.
Umahi said he had directed zonal directors, controllers, resident engineers and contractors to return to construction sites immediately to ensure that failed sections of federal roads were repaired and made motorable within the period.
The intervention covers major highways across the six geopolitical zones.
He warned that contractors executing permanent construction works must not leave other portions of the same roads in deplorable conditions, stressing that motorists should not be made to suffer while construction continues.
“I feel so sad that a contractor will be on site doing permanent work, yet some sections of the roads remain impassable. This practice must stop,” he said.
The minister directed that damaged portions be excavated and rehabilitated with appropriate materials, including asphalt where necessary, rather than allowing potholes and failed sections to remain unattended until the completion of major construction works.
He also instructed ministry officials to document the exercise, engage contractors, report challenges promptly, and ensure that affected roads were restored to acceptable motorable conditions within three weeks.
According to him, the intervention is intended to ease movement during the festive season, facilitate the transportation of goods and services, support the movement of election materials and strengthen security operations ahead of the 2027 general elections.
Umahi urged ministry officials and contractors to treat the assignment with urgency, warning against delays and poor implementation.
No Comment! Be the first one.